Scope
Included the removal and replacement of the 4-storey building façade along Bloor St., demolition of the 6 existing retail units, rough in for the future tenants, and coordination of tenant fit out work requirements. Contacted by the Owner when the project was 50% complete, considerably stalled, and drastically behind schedule. The landlord was very concerned about missing target dates in the new lease agreements and losing tenants.
Solution
THL’s proven Issues Resolution business process quickly identified and assessed numerous design, permit, material, structural and mechanical issues. We developed and implemented various communication, workflow, cost management, and tracking solutions. We overcame design and technical challenges by significantly improving collaboration with construction, architects and consultants, and coordination with tenants. Within 2 months, construction began proceeding at a reasonable rate for tenant turnover, and new target completion dates were then negotiated with all future tenants.
Type
Commercial